Roller Compacted Concrete
Road Construction and More in Montérégie
Over the years, we have had the pleasure of participating in various construction projects throughout Quebec. With our expertise in the field and our ability to meet the demands of large-scale projects, Les Carrières de Saint-Dominique Ltd. has emerged as a preferred partner for any job. Here are some examples of our work.
Ciment Québec
Cimenterie St-Basile-de-Portneuf
Heavy vehicle traffic and parking area.
Area: 9390 m² (or 101,075 sq. ft.)
Thickness: 275 mm (or 11 inches)
Quantity: 2,900 m³ of RCC applied in 4 days
Completed in July 2002
St. Lawrence Stevedoring
Québec City
Steel waste handling and storage area
Area: 12,168 m² (or 130,975 sq. ft.)
Thickness: 300 mm (or 12 inches applied in a single layer)
Quantity: 3,663 m³ of RCC applied in 3 days with two mobile
Pug mill plants
Production rate: ± 250 m3 per hour
Completed in October 2007
Gentilly-2 Nuclear Generating Station
Gentilly
Earthquake resistant slab protection to prevent the dumping of nuclear waste from earthquake resistant reinforced concrete CANSTOR modules.
Quantity: 43,500 m³ of RCC applied in 15 days
Intersection of Highways 15 and 30
Special feature: Two mobile Pug mill factories for the continuous production of RCC
(24 hours a day, seven days a week)
Production rate: ± 250 m3 per hour
Intersection of Highways 15 and 30
Delson-Candiac sector
Road RCC trial by the Québec Ministry of Transport (MTQ)
Project in two phases with a specialized paver and with a fixed 8-metre wide table.
June 2009
Floor area: 2,432 m² (or 26,178 sq. ft.)
Thickness: 250 mm (or 10 inches)
Quantity: 636 m³ of concrete applied in 1 day
Special feature: Expansion joints every 5 linear metres without dowels
October 2010
Area: 800 m² (or 8611 sq. ft.)
Thickness: 250 mm (or 10 inches)
Quantity: 228 m³ of concrete applied in one day
Special feature: Expansion joints every 5 linear metres with dowels
Sobey
Terrebonne Distribution Centre
Heavy vehicle traffic area
Area: 65,063 m² (or 700,330 sq. ft.)
Thickness: 175 mm (or 7 in)
Quantity: 11,953 m³ of RCC applied in 15 days
Completed in July 2011